Mailer 1 – Chapter Registration & Symposium Info – October
Mailer 2 – Individual Registration & Symposium Info – January 2024
Mailer 3 – Final Symposium Info – March 2024
All deadlines are EST. Please note this list is subject to change.
October 31st | Mailer 1 Acknowledgment Form due from each student chapter. |
Mailer 1.5 with local competition rules and additional hotel information sent to each campus chapter. | |
November 1st, by 5:00 pm Eastern Time |
Statement of Intent & Acknowledgement of Eligibility Requirements Form due from each team intending to compete in a Society-wide or Society Pilot Competition – Concrete Canoe, Student Steel Bridge, Sustainable Solutions, Surveying, Construction Institute, Timber-Strong, and 3D Printing. One form is required for each competition and must be filled out by the team captain and faculty advisor. The online form* must be completed by the team captain and faculty advisor(s). Each entity will submit a separate form. * Concrete Canoe forms can be found in the 2025 ASCE Concrete Canoe Request for Proposal Rules. |
The Concrete Canoe Research and Development Schedule and RFQ Pre-Qualification Form are due. | |
Fall Time Frame | Each Timber-Strong Design Build team member who is a builder must complete the Ladder Training Safety online course and submit certification of completion to Cerberus before project work begins. Unique and secure link to be provided to each team from ASCE |
December 1 (postmarked by) | Student Chapter registration is due (see instructions on page 9) |
All deadlines are EST. Please note this list is subject to change.
January 6, by 5:00 pm Eastern Time | Surveying Competition Topographic Mapping Project will be released to teams by 5:00 pm EST on the ASCE UESI Surveying Competition Collaborate Site. |
January 15 | Mailer 2 sent to each student chapter. |
January 31 | Timber-Strong Design Build Phase One Project deliverables are due. (Unique and secure link to be provided to each team from ASCE) |
Mailer 2 Acknowledgement Form Confirmation due from each student chapter. | |
February 1 | ASCE Student Chapter Annual Reports are due by 11:59 pm EST to ASCE. (More information on Annual Reports can be found here. If you have questions on your Annual Report, email [email protected]). Submitting the ASCE Student Chapter Annual Report is an eligibility requirement to compete at the Student Symposia Competitions and to advance to Society-wide Competition Finals. See the eligibility requirements for details. |
ASCE Student Chapter annual dues must be paid, as received by ASCE, no later than 11:59 p.m. EST. Paying ASCE Student Chapter annual dues is an eligibility requirement to compete at the Student Symposia Competitions and to advance to Society-wide Competition Finals. See the eligibility requirements for details. | |
February 3 | ASCE Construction Institute Student Symposium Competition Team Form is due. Links to the form will be sent from ASCE to team captains and faculty advisors per information provided on intent forms. |
February 17 (postmarked by) |
Attendee Registration is due. |
February 13 | Concrete Canoe Project Proposal, Mix Design Sheets, & Materials Notebook due. (Upload to respective folder link provided by ASCE) |
February 24 | Surveying Competition Topographic Mapping Project Plans due by 5:00 pm EST (Unique and secure link to be provided to each team from ASCE) |
February 28 | Timber-Strong Design Build Phase Two Project deliverables are due. (Unique and secure link to be provided to each team from ASCE) |
American Structurepoint, LLC. Concrete Bowling Mix Design and Brief Report due | |
March 1 | Mailer 3 (final) sent to each student chapter. |
March 3 | Water Treatment Competition Final List of Materials are due (sent to [email protected]) |
March 6 | Final Date for Late Registrations |
March 7 | Timber-Strong Design Build Phase Three Project deliverables are due. (Unique and secure link to be provided to each team from ASCE) |
Dr. Kenneth Lauer Symposium Paper submissions are due (sent to [email protected]) | |
March 14 | Sustainable Solutions Competition Technical Design Proposal, Envision Checklist and Criteria Justification, Public Outreach Poster, and Sketchup files are due. (Unique and secure link to be provided to each team from ASCE) |
March 15 | Mailer 3 Acknowledgement Form Confirmation due from each student chapter. |
March 16 | Kittelson & Associates, Inc. Transportation Competition Reports are due (sent to [email protected]) |
March 28 | Timber-Strong Design Build – All Change Orders and final submittals uploaded to ASCE’s Cerberus ftp server. (Unique and secure link to be provided to each team from ASCE) |
Water Treatment Competition Presentations are due (sent to [email protected]) | |
March 30 | Concrete Cornhole Competition Reports are due (sent to [email protected]) |
April 2 | Dr. Kenneth Lauer Symposium Paper presentations are due (sent to [email protected]) |
April 3-5 | 2025 ASCE Indiana-Kentucky Student Symposium |